if 10 man can work 6hours.How many more men are needed towork in 4 hours​

Respuesta :

mathstudent55
mathstudent55 mathstudent55
  • 03-12-2021

Answer:

5 more men

Step-by-step explanation:

10 men do a job in 6 hours.

To do the job in 2 hours, 1/3 of the time, you need 3 times as many men.

30 men do a job in 2 hours.

To do the job in twice the time, 4 hours, you need half the men.

15 men do a job in 4 hours.

15 men - 10 men = 5 men

You need 5 more men.

Answer Link

Otras preguntas

Quick Quiz Question: MAKE YOUR BED and complete the SMART CHOICE Quiz: Name ten different “Smart Choices” you can do in life
4 ejemplos de cine de ciencia ficcion
stuff dudejuststuff​
....help please................
cuestionario de indentificacion de factores de riesgo en viajeros
what is the name of the highest point on most four legged animals?
make a table for f(x) = 2.5x − 10.5 from 2-6. I just need the numbers
2. PART B: Which detail from the text best supports the answer to Part A? A) "Even the sacrifice of staying up late to do something unrelated to school, they se
According to the chart, what are the two most important aspects of personal communication? spoken words and tone of voice tone of voice and nonverbal cues spoke
What is the different food in a life cycle of a froglet inside water? Write each stage name with its specific food.